Contact: Fran Brolley at Community_Relations@ivcc.edu - 815.224.0466

Donate now to the campaign

Capital Campaign
Major Gifts

$1 million – Miller Group Charitable Trust,November 2011
$100,000 -  Bill and Dian Taylor March 2012
$99,000 – USDA Rural Business Enterprise June2012
$25,000 -  IVCC Employee ContributionsJanuary 2012
$9,529 Miscellaneous Contributions
$300,000 – MAG IAS
Total - $1,533,529

CTC Press Releases

State OKs $23 million in CTC funding
CTC funding released
Governor announces CTC funding
IVCC announces $2.1 million campaign for CTC technology
Miller Charitable Trust makes $1 million gift to CTC campaign
IVCC breaks ground on $30.5 million CTC project
IVCC Employees donate $25,000 to CTC campaign
William and Dian Taylor Student Development Commons to honor Winnetka couple’s $100,000 Community Technology Center pledge
Barnes’ donate $1,000 to CTC campaign
$99,000 USDA grant to fund wind equipment
Manufacturing grant funds mechatronics purchase
IVCC partners with manufacturing giants to enhance CTC technology

Current

Peter Miller Community Technology Center Photos and Updates
Peter Miller Community Technology Center Overview
Peter Miller Community Technology Center Groundbreaking
Community Technology Center Capital Campaign
Geothermal Field
Storm Water Detention Pond
Interior Sketches as of February 2012
CTC Prospectus (PDF)

Completed

Natural Science Lab Overview
Ottawa Center Overview
Physical Science Lab Overview
Truck Driver Training Building and Skills Path Overview

History

Construction Projects
Interior Sketches as of February 2012
Loading...

Construction Update week of January 31

Phase 1 - In the next 30 days –
Zinc panel installation and roof copings will continue

First floor – east end
Drywall will be completed and taping will start
Elevator installation will start
Indoor air unit piping will be complete

First floor – west end
Metal stud framing will be complete
Electrical wall rough-ins will start
Indoor air unit piping installation will start

Second floor – east end
Casework installation will continue
Ceiling grid light fixture installation will start
Wood door installation will start

Second floor – west end
Elevator installation will start
Casework installation will start
Light fixture installation will start

Phase 2 – in the next 30 days –

Maintenance Bldg
Finish drywall, tape, prime and paint
Install doors and hardware
Install lights in shop and office area

East Addition
Lay interior block (CMU) walls
Complete metal door frame installation
Mechanical rough-in in block (CMU) walls

PHS Projects
Building A Restroom Stack - Tile work continues at main level. Toilet partition, toilet accessory and fixture installation underway at upper level. Stack A to be complete by 2/5 so work can shift to Building B and abatement work can begin on 2/6.