Construction Update week of January 28
Phase 1 - In the next 30 days –
Zinc panel installation and roof copings will continue
First floor – east end
Drywall will be completed and taping will start
Elevator installation will start
Indoor air unit piping will be complete
First floor – west end
Metal stud framing will be complete
Electrical wall rough-ins will start
Indoor air unit piping installation will start
Second floor – east end
Casework installation will continue
Ceiling grid light fixture installation will start
Wood door installation will start
Second floor – west end
Elevator installation will start
Casework installation will start
Light fixture installation will start
Phase 2 – in the next 30 days –
Maintenance Bldg
Finish drywall, tape, prime and paint
Install doors and hardware
Install lights in shop and office area
East Addition
Lay interior block (CMU) walls
Complete metal door frame installation
Mechanical rough-in in block (CMU) walls
PHS Projects
Building A Restroom Stack - Tile work continues at main level. Toilet partition, toilet accessory and fixture installation underway at upper level. Stack A to be complete by 2/5 so work can shift to Building B and abatement work can begin on 2/6.