Contact: Fran Brolley at Community_Relations@ivcc.edu - 815.224.0466

Donate now to the campaign

Capital Campaign
Major Gifts

$1 million – Miller Group Charitable Trust,November 2011
$100,000 -  Bill and Dian Taylor March 2012
$99,000 – USDA Rural Business Enterprise June2012
$25,000 -  IVCC Employee ContributionsJanuary 2012
$9,529 Miscellaneous Contributions
$300,000 – MAG IAS
Total - $1,533,529

CTC Press Releases

State OKs $23 million in CTC funding
CTC funding released
Governor announces CTC funding
IVCC announces $2.1 million campaign for CTC technology
Miller Charitable Trust makes $1 million gift to CTC campaign
IVCC breaks ground on $30.5 million CTC project
IVCC Employees donate $25,000 to CTC campaign
William and Dian Taylor Student Development Commons to honor Winnetka couple’s $100,000 Community Technology Center pledge
Barnes’ donate $1,000 to CTC campaign
$99,000 USDA grant to fund wind equipment
Manufacturing grant funds mechatronics purchase
IVCC partners with manufacturing giants to enhance CTC technology

Current

Peter Miller Community Technology Center Photos and Updates
Peter Miller Community Technology Center Overview
Peter Miller Community Technology Center Groundbreaking
Community Technology Center Capital Campaign
Geothermal Field
Storm Water Detention Pond
Interior Sketches as of February 2012
CTC Prospectus (PDF)

Completed

Ottawa Center Overview
Natural Science Lab Overview
Physical Science Lab Overview
Truck Driver Training Building and Skills Path Overview

History

Construction Projects
Interior Sketches as of February 2012
Loading...
Construction Update week of 2/12/2013

Phase 1
Zinc panel installation in progress on east and south sides as weather permits
Installation has started for both elevators
Above ceiling inspection by engineers– 2nd floor on Feb. 21

1st Floor – east end
Drywall and soffit work in conference rooms
Taping in progress
Kitchen electric rough-in in progress

1st Floor – west end
Metal framing complete by Feb. 14
Electrical rough-in in progress
Drywall to start the week of Feb. 25

2nd Floor – east end
Painting in progress
Lights, diffusers & sprinkler trim to be complete by Feb. 21
Wood doors to be delivered the week of Feb. 18

2nd Floor – west end
Lights, diffusers & sprinkler trim to be complete by Feb. 18
Painting in progress
Millwork complete by Feb. 18

Phase 2
East Addition Continue interior CMU walls
Continue plumbing and electrical rough-in
Run compressed air lines

Maintenance Bldg Overhead doors ship Feb. 15
Lay floor tile
Substantial completion walk through on March 8

PHS Projects Restroom abatement work has started in Building B.