Week of Nov.12, 2012
Phase 1
Geothermal field and detention pond have been seeded;
Trees were planted Nov. 13;
Stone cropping installation started Nov. 13;
Roofing is complete except for punch list items;
Metal (zinc) panel installation will start Nov. 26;
Trespa composite façade installation will start Nov. 26 or
Dec. 3;
2nd floor mechanical, electrical, and plumbing
work continues;
2nd floor heat pumps and rack delivered
Nov. 13;
2nd floor east end drywall is 65% complete;
1st floor east entrance will be closed in by Nov.
19;
Building will be heated starting the week of Nov. 26;
HVAC ductwork to outside air units is in progress;
Phase 2
Maintenance building concrete floor, stoops and approach are
poured;
East addition CMU west wall is complete;
Electrical switch over to new transformer and gas meter
installation is planned for Nov. 21;
Demolition of Building #10 will start after Thanksgiving.
PHS Projects
Restroom stack A – Demolition by Vanguard is complete.
Asbestos abatement contractors started work on Nov. 12;
Replacement water coolers are operational. Cosmetic finishes
still need to be addressed;
Door hardware restricted keyway is still in progress.