Contact: Fran Brolley at Community_Relations@ivcc.edu - 815.224.0466

Donate now to the campaign

Capital Campaign
Major Gifts

$1 million – Miller Group Charitable Trust,November 2011
$100,000 -  Bill and Dian Taylor March 2012
$99,000 – USDA Rural Business Enterprise June2012
$25,000 -  IVCC Employee ContributionsJanuary 2012
$9,529 Miscellaneous Contributions
$300,000 – MAG IAS
Total - $1,533,529

CTC Press Releases

State OKs $23 million in CTC funding
CTC funding released
Governor announces CTC funding
IVCC announces $2.1 million campaign for CTC technology
Miller Charitable Trust makes $1 million gift to CTC campaign
IVCC breaks ground on $30.5 million CTC project
IVCC Employees donate $25,000 to CTC campaign
William and Dian Taylor Student Development Commons to honor Winnetka couple’s $100,000 Community Technology Center pledge
Barnes’ donate $1,000 to CTC campaign
$99,000 USDA grant to fund wind equipment
Manufacturing grant funds mechatronics purchase
IVCC partners with manufacturing giants to enhance CTC technology

Current

Peter Miller Community Technology Center Photos and Updates
Peter Miller Community Technology Center Overview
Peter Miller Community Technology Center Groundbreaking
Community Technology Center Capital Campaign
Geothermal Field
Storm Water Detention Pond
Interior Sketches as of February 2012
CTC Prospectus (PDF)

Completed

Ottawa Center Overview
Natural Science Lab Overview
Physical Science Lab Overview
Truck Driver Training Building and Skills Path Overview

History

Construction Projects
Interior Sketches as of February 2012
Loading...

Construction Update Week of Oct. 1

 Phase 1

Auditorium roofing underway;

Detention pond and geothermal field work was completed last week;

Landscaping will start the week of Oct. 8;

 Staircase #2 will be installed the week of Oct. 8;

Zinc installation on exterior will start soon;

West entrance drywall to start;

 CMU partitions will be complete by Oct. 5;

Grinded and polished concrete (exposed aggregate) completed this week;

Plumbing rough-in continues;

 Sprinkler installation on second floor started Oct. 1.

Drywall on second floor starts Oct. 15;

Phase 2

Excavation for maintenance building is started;

Moving air compressor in Auto Shop today;

Demolition of Building 5 starts today;

Tree removal scheduled for Oct. 5.