Construction Update Week of Oct. 1
Phase 1
Auditorium roofing underway;
Detention pond and geothermal field work was completed last
week;
Landscaping will start the week of Oct. 8;
Staircase #2 will be installed the week of Oct. 8;
Zinc installation on exterior will start soon;
West entrance drywall to start;
CMU partitions will be complete by Oct. 5;
Grinded and polished concrete (exposed aggregate) completed
this week;
Plumbing rough-in continues;
Sprinkler installation on second floor started Oct. 1.
Drywall on second floor starts Oct. 15;
Phase 2
Excavation for maintenance building is started;
Moving air compressor in Auto Shop today;
Demolition of Building 5 starts today;
Tree removal scheduled for Oct. 5.