Week of Sept. 20, 2012
CTC Project
Phase 1
Site
Signage for Building G and the temporary entrance will be
installed the first week of October;
Pond excavation will be complete the week of Sept. 24,
weather permitting;
Plantings in the pond and geothermal field will start the first
of October;
Building Shell
Lite gauge exterior framing will be complete Sept. 21;
Weather barrier installation to start the week of Sept. 24;
Masonry will be complete the week of Sept. 24;
Roofing continues;
1st Floor
Mechanical piping – mains in progress;
CMU (concrete block) partitions will be complete by Sept.
24;
Stairs were installed on east end;
Metal framing started Sept. 18;
2nd Floor
HVAC duct work in progress;
Interior metal framing in progress;
Mechanical piping and plumbing rough-in in progress.
CTC Project
Phase 2
Excavation for the maintenance facility will start
Sept. 19;
Tree removal is scheduled for the week of Sept. 24;
PHS Projects
Restroom project continues in Building D with electrical rough-in
work and wall board installation;
Tile work will start the week of Sept. 24.