Week of Aug. 27, 2012
CTC Project – Last 30 days
Building Shell
Precast panels complete
90 percent of precast panels grouted and caulked
Roofing continues with two crews working
Main entrance is framed
Exterior wall studs are 95 percent complete
1st Floor
Concrete slab on grade is complete
Interior CMU (concrete block walls) wall partitions 5 to 10
percent complete
Roof drain piping is in progress
Precast insulation is started
MEP (Mechanical, electrical, plumbing) rough-ins started
2nd Floor
Metal stud partitions are in progress
Rigid foam insulation is 80 percent complete
Spray foam insulation is 80
percent complete
Electrical and plumbing rough-ins started
Site
Pond excavation is in progress
Geothermal field – horizontal loop complete and pressure
tested
CTC Project – Next 30 Days
Building Shell
Roofing installation will continue
Precast grouting and caulking will continue
Main entrance metal stud frame will be complete
East entrance metal framing will start
Exterior vapor barrier will be installed
1st Floor
Interior CMU petitions will continue
Precast insulation complete
MEP rough-ins continue
2nd Floor
Metal stud framing will continue
MEP rough-ins will continue
Site
Continue pond excavation
Landscaping of pond and geothermal field will start
CTC Project Phase 2
Asbestos abatement for buildings 5 and 10 is scheduled to
begin on Aug. 29 and be complete by Sept 14.
Anticipate buildings 5 and 10 being available for
construction Sept 17, 2012.
PHS Projects
Plumbing rough-in continues in Building D restroom stack.
Plumber is currently waiting on wall carriers for toilets, urinals and
lavatories to arrive. Plumber reports that carriers were scheduled to arrive on
8/24/12. Electrical rough-in and wall board installation will follow.
Door Panic Hardware Replacement work has started. Contractor
has all hardware on site with exception of key cylinders.