Update as of August 14
CTC
Phase 1
Site
Work
·
Geothermal field site preparation for
landscaping to start soon
·
Pond excavation will resume Aug. 15
·
Trench by softball field is being filled and
leveled; excess dirt will be removed
CTC
Building
·
Precast panel installation will be complete by
Aug. 20 and then interior caulking will start
·
Interior rigid insulation of precast will start
Aug. 20
·
Slab on grade concrete will be complete Aug. 17
·
Roofing started Aug. 7
·
Masonry work will begin Aug. 23
·
Construction of stairs between stories will
start the week of Sept. 3
CTC
Phase 2
·
Asbestos Abatement will start Aug. 27 on buildings 5 and 10
·
General Contractor will start by mid-September
on buildings 5 and 10 and the maintenance building