Construction Update as of August 7
CTC Phase 1
Site Work
·
Geothermal horizontal loops are connected
·
Geothermal field site preparation for
landscaping will start Aug. 13
Pond excavation will resume Aug. 13
Trench by softball field is being filled and
leveled; excess dirt will be removed on Aug. 15
CTC Building
·
Precast panel installation will start Aug. 10
and be complete within two weeks and then interior caulking will start
·
Rigid installation will arrive Aug. 15;
perimeter interior framing and measuring for windows will start
·
Roofing started Aug. 7
Masonry work will begin the week of Aug. 13,
starting with interior work on elevator shafts
Construction of stairs between stories will
start the week of Aug. 27
CTC Phase 2
·
Asbestos Abatement will start Aug. 20 on
buildings 5 and 10
·
General Contractor will start by mid-September
on buildings 5 and 10 and the maintenance building
PHS Projects
1. Classroom
ceiling abatement work was completed Aug. 3
2. Demolition
work in Building D restroom stack was complete Aug. 3
Week of August 6, 2012:
3. Start
new plumbing pipe rough-in at Building D restroom stack. Plumbers are scheduled
on-site Monday. Electricians will follow later in the week.
4. Complete
floor leveling to anticipate future tile work.