Construction Update week of July 16
Geothermal horizontal loop to be complete by August 10
Underground electrical work to be complete by July 30
Structural steel detailing to be complete by July 20.
Lite gauge exterior metal framing is ongoing
Concrete pour on roof deck started July 17
Slab on grade (first floor) concrete to be complete by
August 3
Precast concrete erection will start August 3
Roofing will start August 1; the existing auditorium will be
first
Masonry work will start in mid August