Construction Update Week of July 9
Geothermal horizontal loop to be complete by Aug. 10
Underground electrical work to be complete by July 30
Steel columns and metal decking will be complete by July 13
Slab on grade (first floor) poured July 9 for first 2/3’s;
last 1/3 will start July 18
Last 1/3 of 2nd floor deck will be poured the
week of July 16
2nd floor mechanical/electrical/plumbing rough-in
will start July 16
Precast concrete erection will start July 30
Roofing will start in three to four weeks; the existing
auditorium will be first