Construction Update Week of June 18
Building G (Therapeutic Massage)
·
Substantially
completed – June 12 – building was turned over to the College for occupancy;
·
Therapeutic Massage
will move from Building 11 in early July
Geothermal Field
·
Geothermal
horizontal loop started June 18 and
will take about six weeks
CTC
·
Steel erection continues – two
thirds of steel frame is in place and two thirds of
metal decking is in place;
·
Underground
plumbing will be complete by June 21;
·
Underground
electrical is ongoing;
·
Second
floor deck concrete on two thirds of building will be poured June 25; last
portion the week of July 30;
·
Light
gauge exterior metal framing will start June 25;
·
Slab on
grade (non polished) will be poured the week of July 2;
·
Replace
roof on original building F in two to three weeks;
·
Precast
concrete wall erection will start the first or second week of August;
Site
Work
·
Pond excavation will be complete by June 29
·
Fire lane will be paved the first week of
July
