Week of June 11Construction Update
Building C
·
Boards
covering the windows in the Board Room, President’s Office, east Building C
hallway, and Records and Admissions will be removed within one to two weeks
Geothermal Field
·
Geothermal
horizontal loop will start June 18 and
take about six weeks.
Building G (Therapeutic Massage)
·
Substantially
completed – June 12 – building was turned over to the College for occupancy
·
Therapeutic Massage
will move from Building 11 in early July
CTC
·
Steel
erection continues – two thirds of steel frame is in place
·
Underground
plumbing will be complete by June 15
·
Underground
electrical is ongoing
·
Second
floor deck will be poured June 25
·
Light
gauge exterior metal framing will start June 25
·
Precast
concrete wall erection will start the first or second week of August