Week of May 14
Building C
·
Additional concrete for the Building C sidewalk by
the temporary entrance to adjust slope will be done on a Friday
afternoon when there are fewer people on campus due to the pedestrian traffic
in that area. This has been delayed because of rain, aiming for May 18 now.
·
Windows
in the Board Room, President’s Office, east Building C hallway, and Records and
Admissions will be boarded up May 21 in preparation for steel erection on the
CTC
Geothermal Field
·
Drilling
and grouting will be completed today
·
Backfill
of the field will start tomorrow
·
Topsoil
will be moved from the CTC site to the geothermal field
·
Pipe will
be run from the geothermal field to the corner of the new building May 21
-25 (under roadway and temporary sidewalk)
·
Pipe
installation in the horizontal field will start the week of June 11 (will take
approximately six weeks)
Building G (Therapeutic Massage)
·
Plumbing and glazing
(mirrors) will be completed by May 18
·
Substantial completion
– June 12 (punch list items will still need to be addressed)
CTC
·
Masonry
will start tomorrow at the corner of the theatre
·
Steel
erection is scheduled to start on May 29 starting at the west end
·
Foundations
walls, piers, and footings will be complete by May 31