Construction Update April 30
Building C
Additional concrete for the Building C sidewalk by the temporary entrance to adjust slope will be done on a Friday.
Windows in the Board Room, President’s Office, east
Building C hallway, and Records and Admissions will be boarded up May 21
in preparation of steel erection for the CTC
Geothermal Field
As of April 30, 125 wells, each over 500’ deep, have been drilled. Four rigs are working
Building G
Carpeting will be completed by May 4
Millwork (cabinetry) is installed
Substantial completion is expected by June 12
CTC
Foundations should be complete by May 28
Elevator pits are in and shafts are drilled
Steel erection is scheduled to start the week of May 21