Building
C
Final
work on temporary entrance – finish door hardware, install glass – week of
April 16
Caulk wall around concrete pillar,
ceiling – week of April 16
Geothermal
Field
Three
rigs drilling at the rate of one well per day per rig. An estimated 192 wells will be drilled.
Building G
Painting is
completed
Millwork
(cabinetry) to be installed week of April 23
Ceramic tile to
be installed week of April 30
Site
Ameren
will lay new electrical lines the week of April 16
Electrical
tie-in is scheduled for a Sunday –April 29– power will be shut to entire campus
that day CTC
Foundations
for new building are started
Steel
erection is scheduled to start the week of May 4