Construction Update Week of April 3
Miller Building Clearing the way http://www.screencast.com/t/4Uz1x4Co5
Miller building April 3 http://www.screencast.com/t/WzurUHHaz
Geothermal Field· Drilling
began Tuesday with one drilling rig; April 10 two more rigs should start
drilling. The normal rate of drilling is one well/day/rig. This means it will
take approximately two months to complete the drilling in the geothermal field.
Building G
· Painting underway
· Millwork
(cabinetry) to be installed week of April 23
· Ceramic
tile to be installed week of April 30
Site
· Water
tie-in is now scheduled for 4pm Friday, April 6– water will be shut off to
entire campus for approximately four hours
· Ameren
will lay new electrical lines the week of April 6
· Electrical
tie-in is scheduled for a Sunday – April 22 or April 29– power will be shut to
entire campus that day
· Foundations
for new building are started· Steel erection is scheduled to start the week of
May 4