
Donate now to the Peter Miller Community Technology Center capital campaign.
Peter Miller Community Technology Center
Video, Photos and Updates
Construction Update Week of May 13
Phase 1
Site work
Storm piping installation will start May 16
Tree removal will take place this week or next – a total of
four trees – three in the construction area and the one hit by lightning
Concrete curbs will be poured the week of May 20
Building Shell
Roof copings and metal panel installation are in progress on
the north side
First Floor
Millwork installation is in progress
Kitchen equipment is being installed
Low voltage cabling is in progress
Second Floor
Toilet partition installation will start May 15
Flooring in progress
Ceiling tile installation in progress
Equipment Startup
Water source heat pumps are up and running
Lighting control programming will start the week of June 10
Low voltage cabling testing will start the week of June 10
Phase 2
East Addition
Drywall and painting continues
Air conditioner pads are poured
Water lines and HVAC duct work are being installed
West Addition
Laying CMU (concrete block) walls
Plumbing and electrical are being roughed in
Site Work
Coring out driveway north of east addition
Storm sewer by greenhouse is installed
Cutting and filling new road to maintenance building
Welding/Auto Shop
Sprinkler piping started May 14
New man door to be installed this week
Demolition of siding and installation of new siding
Week of Apr. 30
Week of Apr. 23
Week of Apr. 16
Week of Apr. 9

.jpg)
.jpg)
Week of Apr. 3
Week of Mar. 19
Week of Mar. 12
Week of Mar. 5
Week of Feb. 26
Week of Feb. 19
Week of Feb. 12


Week Feb. 6
Week of Jan. 31
Week of Jan. 28
Week of Jan. 16
Week of Jan. 7
Week of Dec. 10


Week of Dec. 3


Week of Nov.12
Week of Oct. 8, 2012



Week of Oct. 1 Construction Update
Week of Sept. 20, 2012
Week of Sept. 10, 2012


Week of Aug. 27


Week of Aug 14
Week of Aug 7

.jpg)

.jpg)

Construction Update - July 31
Week of July 16(2)



week of july 9
Week of June 25

.jpg)
Photo courtesy of Tom Sistak of the Times
Week of June 18

Week of June 11



Week of May 28



Week of May 21
CTC video foundation forms

Week of May 14
Excavation
Geothermal drilling
Bulldozer
Demo work
Foundation work
Webcam stills
Week of May 7


.JPG)
Week of April 30
Construction video http://www.screencast.com/t/4Uz1x4Co5
Construction video 2 http://www.screencast.com/t/WzurUHHaz
Week of April 16
Week of April 3


Week of March 26







Previous Update Links and Photos:
Week of March 19





Week of March 13

Week of February 28

Week of February 21


Week of February 15
Week of February 8
Miller Charitable Trust Announces $1 Million Gift for IVCC
Governor Quinn Announces Funding